Project Update: September 1 - Bridge Repairs on CO 257

There is an upcoming 20-day closure of CO 257 from south of Crossroads Blvd. to just north of US 34 (10th St.) in Greeley, weather permitting. During this time, commuters will have to detour.

Work will take place from 7 a.m. on Tuesday, September 5 through 7 p.m. on Monday, September 25. Planned work includes the resurfacing of CO 257, extensive repairs to the bridge supports and deck, replacing bridge railing and paving the bridge. Vehicle traffic must stay off the bridge while work is performed.

The Town of Windsor’s Eastman Park Dr. and CO 257 intersection improvements continue and is nearing completion. Following the reopening both the northbound and southbound portion of the intersection, the next steps are to install traffic signal poles, coordinate with Great Western Railway to synchronize their crossing signals with the new traffic signals, and pave the east/west portion of Eastman Park Dr. from the Cornerstone Dr. roundabout to CO 257. If all goes to plan, the intersection is anticipated to open in October – nearly 3-4 months earlier than originally projected.


Share Project Update: September 1 - Bridge Repairs on CO 257 on Facebook Share Project Update: September 1 - Bridge Repairs on CO 257 on Twitter Share Project Update: September 1 - Bridge Repairs on CO 257 on Linkedin Email Project Update: September 1 - Bridge Repairs on CO 257 link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>