Project Update: April 29

The field lighting, parking lot lighting and required electrical infrastructure have all been installed. As of Friday, April 24, the lighting system has been commissioned by the installation contractor and turned over to the lighting manufacturer for operation.

Post-installation lighting tests will be conducted over the next several weeks to ensure proper performance and functionality.

In addition, the project is currently preparing a submission for certification with DarkSky International for outdoor sports lighting.