March 2026 Update
Design work is currently underway for the widening of East Harmony Road between County Road 15 and State Highway 257. The project is progressing through the 60% design phase, which includes development of roadway plans, drainage design, traffic signal and intersection evaluations, survey work, geotechnical investigation, pavement design, and easement determination. This phase of design is anticipated to be completed by the end of 2026.
To date, the survey, geotechnical report, and pavement design have been completed. The consulting engineer is continuing work on roadway plans, drainage design, and traffic signal and intersection evaluations as the project advances through the remaining elements of the 60% design phase.