Project Update: September 18
Construction for the new Wastewater Treatment Facility Headworks building is anticipated to start in the fall. Currently, town and project staff are finalizing final stages of design and contract review, then groundbreaking will commence.
The new building construction serves as the initial processing stage where incoming wastewater is prepared for further treatment. It includes screening to remove large debris and grit removal to eliminate heavy particles that could damage equipment. The building will also feature systems for measuring wastewater flow and may involve the addition of chemicals to adjust pH levels or aid in contaminant removal. By handling these preliminary tasks, the headworks building ensures that the wastewater entering the main treatment processes is cleaner and more manageable, enhancing the overall efficiency of the treatment plant.