7th Street Bridge Rehabilitation

Share 7th Street Bridge Rehabilitation on Facebook Share 7th Street Bridge Rehabilitation on Twitter Share 7th Street Bridge Rehabilitation on Linkedin Email 7th Street Bridge Rehabilitation link

The 7th St. bridge over the Cache la Poudre River has several areas of deterioration that need to be repaired, which will result in a full closure of 7th St. between Eastman Park Dr. and Laku Lake Rd.

To accomplish the repairs, the existing asphalt road deck will be removed, allowing crews to make repairs to the bridge’s sub-structure from above, significantly lowering costs and improving the timeframe of the closure.

Once repairs to the sub-structure are complete, a new concrete road deck will be installed, which will increase the overall lifespan of the bridge by 15 to 25 years.

In addition to the closure of 7th St., the Poudre River Trail—which runs underneath the bridge—will also be closed in that section during the course of the project.

The 7th St. bridge over the Cache la Poudre River has several areas of deterioration that need to be repaired, which will result in a full closure of 7th St. between Eastman Park Dr. and Laku Lake Rd.

To accomplish the repairs, the existing asphalt road deck will be removed, allowing crews to make repairs to the bridge’s sub-structure from above, significantly lowering costs and improving the timeframe of the closure.

Once repairs to the sub-structure are complete, a new concrete road deck will be installed, which will increase the overall lifespan of the bridge by 15 to 25 years.

In addition to the closure of 7th St., the Poudre River Trail—which runs underneath the bridge—will also be closed in that section during the course of the project.

  • Project Update: May 16

    Share Project Update: May 16 on Facebook Share Project Update: May 16 on Twitter Share Project Update: May 16 on Linkedin Email Project Update: May 16 link

    Beginning Tuesday, May 27, 7th St. will be closed from the Eastman Park Dr. roundabout to Laku Lake Rd., the entrance to the Eastman Park South Expansion, for bridge rehabilitation. The closure will remain in place throughout the summer, weather permitting.

    During this time, all traffic—including motorists, bicyclists and pedestrians—will be required to detour.

    Motorists

    Detour via Crossroads Blvd., CO 257, and Eastman Park Dr.

    Cyclists

    • Those traveling on the Poudre River Trail (north of the closure) should detour via Eastman Park Dr. and Water Valley Pkwy.
    • Those on 7th St. (south of the closure) should detour via Laku Lake Road, the Poudre River Trail through Eastman Park, Eastman Park Drive, and Water Valley Parkway.

    Pedestrians

    Remain on sidewalks and avoid the active construction zone. Those walking along the Poudre River Trail should detour via Eastman Park Dr. and Water Valley Pkwy.

    Eastman Park River Experience Users

    Exercise extreme caution due to fast river flow rates. Tubers, kayakers and paddleboarders are advised to exit the river before passing under the 7th St. bridge construction zone.

    This project involves complex coordination with CDOT, environmental protections for the Cache la Poudre River, and efforts to maintain access to Eastman Park and related programming. The community’s continued patience and cooperation throughout the duration of the work is extremely appreciated!

    To receive traffic alerts, text WINDSORROADS to 888777.

    Detour Map


  • Project Update: May 6

    Share Project Update: May 6 on Facebook Share Project Update: May 6 on Twitter Share Project Update: May 6 on Linkedin Email Project Update: May 6 link

    Following the end of the school year, the town will commence the 7th Street Bridge Rehabilitation Project, which will require a full closure of 7th St. from Eastman Park Drive to Laku Lake Rd. through August, weather permitting.

    Significant traffic delays and congestion are expected throughout the duration of the project, and motorists are strongly encouraged to plan alternate routes in advance, particularly if accessing Eastman Park, the Eastman Park River Experience or Our Lady of the Valley Catholic Church.

  • Project Update: July 11, 2024

    Share Project Update: July 11, 2024 on Facebook Share Project Update: July 11, 2024 on Twitter Share Project Update: July 11, 2024 on Linkedin Email Project Update: July 11, 2024 link

    Project Delay Notice: Please be advised that the current Capital Improvement Project (CIP) is experiencing delays and is now scheduled for completion in 2025 or beyond, pending future budget approvals. For any inquiries or clarifications regarding this delay, please contact the project manager directly using the contact listed under the “Who’s Listening” section. We appreciate your patience and understanding.