Project Update: August 1
Crews successfully poured the concrete for the bridge deck earlier this week, marking a significant milestone in the 7th Street Bridge Rehabilitation Project. The bridge deck forms the primary surface of the bridge that vehicles will eventually travel on, and this progress brings the project one step closer to completion.
As of Friday, August 1, crews are scheduled to install the expansion joint, which allows the bridge to safely expand and contract with changing temperatures. Following that, asphalt paving is expected to take place during the week of August 4. These final construction activities are essential to preparing the bridge for safe public use.
The project remains on schedule and continues to move toward an early August reopening. Thank you for your continued interest and support. Future updates will be provided as the bridge nears completion.