This project has been completed.
Steeplechase Drive runs east and west through the Steeplechase neighborhood in south Windsor. The roadway connects with New Liberty Road and intersects with major thoroughfares including Colorado Boulevard (County Road 13) and Fairgrounds Avenue. Town staff have been studying Steeplechase Drive and planning improvements in response to resident concern, vehicle speeding and community growth.
Steeplechase Drive runs east and west through the Steeplechase neighborhood in south Windsor. The roadway connects with New Liberty Road and intersects with major thoroughfares including Colorado Boulevard (County Road 13) and Fairgrounds Avenue. Town staff have been studying Steeplechase Drive and planning improvements in response to resident concern, vehicle speeding and community growth.
Share April Project Update on FacebookShare April Project Update on TwitterShare April Project Update on LinkedinEmail April Project Update link
Roadway striping operations are on the schedule! Please expect delays while work is underway.
Traffic Alert: Roadway striping is scheduled for Steeplechase Drive between Colorado Boulevard and Horizon Ridge Drive April 18 through April 22, weather permitting. The roadway will remain open, but delays are anticipated.
Share January Project Update on FacebookShare January Project Update on TwitterShare January Project Update on LinkedinEmail January Project Update link
Happy 2022! We wanted to give a formal update about the project to address what work has been completed and what residents can expect. Since our community open house, we have completed the following:
Installed two speed limit signs (one in each direction) to alert drivers of their speeds and encourage safe driving.
Replaced yield signs along the corridor to stop signs.
Developed a striping plan that narrows travel lanes for speed mitigation and safety aspects discussed at the open house and summarized in the previous corridor study.
Town Engineering staff were planning to implement the roadway striping changes this past fall, but due to supply chain issues and contractor availability, work has been delayed until this spring. We apologize for the delay and look forward to implementing our striping plan as soon as weather conditions allow and we’re able to get contractors scheduled.
Share August 2021 Community Meeting on FacebookShare August 2021 Community Meeting on TwitterShare August 2021 Community Meeting on LinkedinEmail August 2021 Community Meeting link
Thanks to everyone that participated in the August 5 community meeting. We appreciated your thoughts and feedback. If you couldn’t attend, feel free to review the meeting materials below, including the meeting PowerPoint, frequently asked questions and a meeting recording.
Residents can expect to see roadway restriping and the installation of two speed feedback signs in the next few months. Long-term plans include installing crosswalks and collecting additional traffic data. View the meeting materials for more details.