New Wastewater Treatment Headworks Construction

Share New Wastewater Treatment Headworks Construction on Facebook Share New Wastewater Treatment Headworks Construction on Twitter Share New Wastewater Treatment Headworks Construction on Linkedin Email New Wastewater Treatment Headworks Construction link

The new headworks building will continue making the wastewater treatment process more efficient by increasing the capabilities and capacity of the pre-treatment process. Improvements will include new screening and grit removal equipment and upgrades to the existing pump and electrical infrastructure. This effort will enable the future expansion of the facility to handle increased capacity demands.

Windsor’s Wastewater Treatment Facility has been operational since the 1990s and has consistently been able to meet or exceed all permit requirements and return clean, treated water back to the Cache la Poudre River. The headworks facility is the first step in the wastewater treatment process: removing trash and inorganic material, such as sand, grit, eggshells, etc. from the wastewater entering the facility.

The new headworks building will continue making the wastewater treatment process more efficient by increasing the capabilities and capacity of the pre-treatment process. Improvements will include new screening and grit removal equipment and upgrades to the existing pump and electrical infrastructure. This effort will enable the future expansion of the facility to handle increased capacity demands.

Windsor’s Wastewater Treatment Facility has been operational since the 1990s and has consistently been able to meet or exceed all permit requirements and return clean, treated water back to the Cache la Poudre River. The headworks facility is the first step in the wastewater treatment process: removing trash and inorganic material, such as sand, grit, eggshells, etc. from the wastewater entering the facility.

  • Project Update: March 20

    Share Project Update: March 20 on Facebook Share Project Update: March 20 on Twitter Share Project Update: March 20 on Linkedin Email Project Update: March 20 link

    Construction of the new headworks facility at Windsor’s Wastewater Treatment Facility is now approximately 80% complete and remains on schedule for a May/June startup.

    Crews are currently completing final interior work, including HVAC installation, electrical systems, equipment outfitting and protective coatings.

    Once the new headworks facility is operational, the existing headworks building will be converted into an influent pump station. The new pump station will significantly increase system capacity, with one new pump having the ability to handle approximately three times the capacity of a single existing pump. The upgraded system will also utilize coarse screens instead of fine screens, which better align with the new facility design.

    The most complex phase currently underway involves retrofitting the new system to connect with the existing headworks building, ensuring the upgraded infrastructure integrates smoothly with the current wastewater system.

  • Project Update: January 27

    Share Project Update: January 27 on Facebook Share Project Update: January 27 on Twitter Share Project Update: January 27 on Linkedin Email Project Update: January 27 link

    Construction on the Windsor Wastewater Treatment Facility (WWTF) Headworks Building is now underway, marking the next step toward upgrading the facility. A contractor for construction has been identified and has kicked off the work by locating existing utilities and preparing the site for excavation. This crucial phase ensures the site is fully ready for the new building foundation, which will support the upgraded infrastructure. Crews are working to ensure a smooth transition into the next phase of construction. The first concrete pour is currently anticipated for early February, weather permitting, which will be a major milestone for the project. Once completed, these improvements will help enhance the facility's performance and efficiency, benefiting the community by improving wastewater treatment processes and ensuring long-term sustainability.

  • Project Update: September 18

    Share Project Update: September 18 on Facebook Share Project Update: September 18 on Twitter Share Project Update: September 18 on Linkedin Email Project Update: September 18 link

    Construction for the new Wastewater Treatment Facility Headworks building is anticipated to start in the fall. Currently, town and project staff are finalizing final stages of design and contract review, then groundbreaking will commence.

    The new building construction serves as the initial processing stage where incoming wastewater is prepared for further treatment. It includes screening to remove large debris and grit removal to eliminate heavy particles that could damage equipment. The building will also feature systems for measuring wastewater flow and may involve the addition of chemicals to adjust pH levels or aid in contaminant removal. By handling these preliminary tasks, the headworks building ensures that the wastewater entering the main treatment processes is cleaner and more manageable, enhancing the overall efficiency of the treatment plant.

Page last updated: 20 Mar 2026, 10:55 AM