Project Update: January 27
Construction on the Windsor Wastewater Treatment Facility (WWTF) Headworks Building is now underway, marking the next step toward upgrading the facility. A contractor for construction has been identified and has kicked off the work by locating existing utilities and preparing the site for excavation. This crucial phase ensures the site is fully ready for the new building foundation, which will support the upgraded infrastructure. Crews are working to ensure a smooth transition into the next phase of construction. The first concrete pour is currently anticipated for early February, weather permitting, which will be a major milestone for the project. Once completed, these improvements will help enhance the facility's performance and efficiency, benefiting the community by improving wastewater treatment processes and ensuring long-term sustainability.