Background

The East Harmony Rd Widening is a major project to reduce traffic congestion in Windsor. The widening is a high priority in Windsor’s Transportation Master Plan and is expected to benefit local residents, commuters and regional truck traffic.

Design work for the project started earlier this year and will continue throughout 2026. The design team will continue refining plans and begin acquiring the necessary right-of-way (ROW) for the road. Once complete, the East Harmony Rd Widening will improve traffic flow, reduce congestion in the area and provide better access for both locals and visitors.

Timeline

The town is in the initial phases of design and outreach. Preliminary design (60%) is ongoing and expected to continue through 2026. A timeline for final design and construction of the proposed improvements will be established once funding for the project is secured.

Background

The East Harmony Rd Widening is a major project to reduce traffic congestion in Windsor. The widening is a high priority in Windsor’s Transportation Master Plan and is expected to benefit local residents, commuters and regional truck traffic.

Design work for the project started earlier this year and will continue throughout 2026. The design team will continue refining plans and begin acquiring the necessary right-of-way (ROW) for the road. Once complete, the East Harmony Rd Widening will improve traffic flow, reduce congestion in the area and provide better access for both locals and visitors.

Timeline

The town is in the initial phases of design and outreach. Preliminary design (60%) is ongoing and expected to continue through 2026. A timeline for final design and construction of the proposed improvements will be established once funding for the project is secured.

  • March 2026 Update

    Share March 2026 Update on Facebook Share March 2026 Update on Twitter Share March 2026 Update on Linkedin Email March 2026 Update link

    Design work is currently underway for the widening of East Harmony Road between County Road 15 and State Highway 257. The project is progressing through the 60% design phase, which includes development of roadway plans, drainage design, traffic signal and intersection evaluations, survey work, geotechnical investigation, pavement design, and easement determination. This phase of design is anticipated to be completed by the end of 2026.

    To date, the survey, geotechnical report, and pavement design have been completed. The consulting engineer is continuing work on roadway plans, drainage design, and traffic signal and intersection evaluations as the project advances through the remaining elements of the 60% design phase.


    Design work is currently underway for the widening of East Harmony Road between County Road 15 and State Highway 257. The project is progressing through the 60% design phase, which includes development of roadway plans, drainage design, traffic signal and intersection evaluations, survey work, geotechnical investigation, pavement design, and easement determination. This phase of design is anticipated to be completed by the end of 2026.

    To date, the survey, geotechnical report, and pavement design have been completed. The consulting engineer is continuing work on roadway plans, drainage design, and traffic signal and intersection evaluations as the project advances through the remaining elements of the 60% design phase.