New Wastewater Treatment Headworks Construction

Share New Wastewater Treatment Headworks Construction on Facebook Share New Wastewater Treatment Headworks Construction on Twitter Share New Wastewater Treatment Headworks Construction on Linkedin Email New Wastewater Treatment Headworks Construction link

Windsor’s Wastewater Treatment Facility has been operational since the 1990s and has consistently been able to meet or exceed all permit requirements and return clean, treated water back to the Cache la Poudre River. As the population in Windsor continues to steadily increase, so does the need for updated sewer infrastructure. The headworks facility is the first step in the wastewater treatment process: removing trash and inorganic material, such as sand, grit, eggshells, etc. from the wastewater entering the facility. The new headworks building will update and increase the capacity of the screening and grit removal processes.

The most recent update to Windsor’s Wastewater Treatment Facility was completed in the fall of 2023 with the new biosolids facility. The biosolids facility increased the efficiency and capacity of the solids treatment, dewatering, and disposal processes.

The new headworks building will continue making the wastewater treatment process more efficient by increasing the capabilities and capacity of the pre-treatment process. The new headworks building construction will include new screening and grit removal equipment with improvements to the existing pump and electrical infrastructure. The new construction and improvements will increase the treatment capacity of the pre-treatment process from 2.8 million gallons per day to 7.5 million per day.

Windsor’s Wastewater Treatment Facility has been operational since the 1990s and has consistently been able to meet or exceed all permit requirements and return clean, treated water back to the Cache la Poudre River. As the population in Windsor continues to steadily increase, so does the need for updated sewer infrastructure. The headworks facility is the first step in the wastewater treatment process: removing trash and inorganic material, such as sand, grit, eggshells, etc. from the wastewater entering the facility. The new headworks building will update and increase the capacity of the screening and grit removal processes.

The most recent update to Windsor’s Wastewater Treatment Facility was completed in the fall of 2023 with the new biosolids facility. The biosolids facility increased the efficiency and capacity of the solids treatment, dewatering, and disposal processes.

The new headworks building will continue making the wastewater treatment process more efficient by increasing the capabilities and capacity of the pre-treatment process. The new headworks building construction will include new screening and grit removal equipment with improvements to the existing pump and electrical infrastructure. The new construction and improvements will increase the treatment capacity of the pre-treatment process from 2.8 million gallons per day to 7.5 million per day.

  • Project Update: September 18

    Share Project Update: September 18 on Facebook Share Project Update: September 18 on Twitter Share Project Update: September 18 on Linkedin Email Project Update: September 18 link

    Construction for the new Wastewater Treatment Facility Headworks building is anticipated to start in the fall. Currently, town and project staff are finalizing final stages of design and contract review, then groundbreaking will commence.

    The new building construction serves as the initial processing stage where incoming wastewater is prepared for further treatment. It includes screening to remove large debris and grit removal to eliminate heavy particles that could damage equipment. The building will also feature systems for measuring wastewater flow and may involve the addition of chemicals to adjust pH levels or aid in contaminant removal. By handling these preliminary tasks, the headworks building ensures that the wastewater entering the main treatment processes is cleaner and more manageable, enhancing the overall efficiency of the treatment plant.

Page last updated: 18 Sep 2024, 01:12 PM