The Town of Windsor has adopted plans to install sports field lighting at the Chimney Park Ballfields as part of its ongoing investment in community recreation. Chimney Park is a central hub for a wide range of activities, including youth and adult sports leagues, tournaments, practices and community gatherings. As participation continues to grow, demand for field time has increased, especially during peak seasons when daylight hours are limited.
Installing field lighting will allow the ballfields to be used safely and efficiently during evening hours, helping reduce scheduling conflicts, limit wear on other parks and maximize the use of existing facilities. This improvement supports local families, athletes, and organizations by providing more flexible scheduling options, expanding access to recreational programs and ensuring Windsor’s parks continue to meet the needs of a growing and active community.
The Town of Windsor has adopted plans to install sports field lighting at the Chimney Park Ballfields as part of its ongoing investment in community recreation. Chimney Park is a central hub for a wide range of activities, including youth and adult sports leagues, tournaments, practices and community gatherings. As participation continues to grow, demand for field time has increased, especially during peak seasons when daylight hours are limited.
Installing field lighting will allow the ballfields to be used safely and efficiently during evening hours, helping reduce scheduling conflicts, limit wear on other parks and maximize the use of existing facilities. This improvement supports local families, athletes, and organizations by providing more flexible scheduling options, expanding access to recreational programs and ensuring Windsor’s parks continue to meet the needs of a growing and active community.
Share Project Update: April 29 on FacebookShare Project Update: April 29 on TwitterShare Project Update: April 29 on LinkedinEmail Project Update: April 29 link
The field lighting, parking lot lighting and required electrical infrastructure have all been installed. As of Friday, April 24, the lighting system has been commissioned by the installation contractor and turned over to the lighting manufacturer for operation.
Post-installation lighting tests will be conducted over the next several weeks to ensure proper performance and functionality.
In addition, the project is currently preparing a submission for certification with DarkSky International for outdoor sports lighting.
The field lighting, parking lot lighting and required electrical infrastructure have all been installed. As of Friday, April 24, the lighting system has been commissioned by the installation contractor and turned over to the lighting manufacturer for operation.
Post-installation lighting tests will be conducted over the next several weeks to ensure proper performance and functionality.
In addition, the project is currently preparing a submission for certification with DarkSky International for outdoor sports lighting.